• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2014 - Apr 2014
  • Estimated project cost $140,714
  • Australian Government contribution $140,714
  • Local Council/Shire Lockyer Valley Regional Council
  • State QLD

Project description

The existing surface had began to lose its stone causing poor surface layer that was breaking up.

Construct a new bitumen seal to correct the issue with the surface

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.