The project will upgrade approximately 6.8 kilometres of Narellan Road between Camden Valley Way at Narellan and Blaxland Road in Campbelltown to a six-lane divided road.
The upgrade will enable Narellan Road to support the increased growth in demand associated with the South West Growth Centre.
The Australian Government is providing $62.9 million towards the construction of this project.
On 23 May 2014, BMD Constructions Pty Ltd was awarded the contract for the construction of Stage One of the Narellan Road Upgrade. Construction commenced on 23 July 2014 and was completed in March 2016.
On 23 October 2015, Seymour Whyte Constructions Pty Ltd was awarded the contract for the construction of Stage Two. Construction commenced in December 2015 and was completed in April 2018.
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.