• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Late 2014 - Mid 2015
  • Estimated project cost $2,333,372
  • Australian Government contribution $1,866,698
  • Local Council/Shire Northern Midlands Council
  • State TAS
  • Corridor Hobart - Burnie

Project description

The project widened the Midland Highway at Conara to provide a northbound slow vehicle turn out lane from Esk Main Road to Panec Street.

Benefits

The project achieved a 3 Star AusRAP Safety Rating on this section of the Midland Highway. The project improved safety, capacity and overtaking opportunities.

Funding

The cost of the project was $2,333,372. The Australian Government contributed $1,866,698 and the Tasmanian Government $466,674.

Timetable

Construction commenced in November 2014 and was completed in May 2015.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.