• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2013 - Jun 2014
  • Estimated project cost $135,792
  • Australian Government contribution $135,792
  • Local Council/Shire Southern Midlands Council
  • State TAS

Project description

Deteriorated road pavement due to age of seal and sub-base. Evidence of cracking and potholes which will require repair and reseal of pavement.

Reconstruct and seal 1.0 kilometre of sealed road to a width of 5.50 metres. The reconstruction process will involve excavation of side drains, placement of additional road base materials, re-stabilisation and seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.