• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2013 - Feb 2014
  • Estimated project cost $540,000
  • Australian Government contribution $369,136
  • Local Council/Shire District Council of Mount Barker
  • State SA

Project description

Road surface is very degraded and pot holed and intersection to be realigned to improve safety.

Remove existing road base, construction of kerb, gutter, drainage and apply new base course and asphalt to all sections of roadway. Includes construction of pedestrian crossings.

Total cost of proposed project is $540,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.