• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2013 - Apr 2014
  • Estimated project cost $274,000
  • Australian Government contribution $119,583
  • Local Council/Shire Huon Valley Council
  • State TAS

Project description

Road has multiple failures in the seal and substructure with clay infiltration.

Road will be lime stabilised with 120 millimetres finely crushed rock overlay then will be finished with a two coat seal. Installation of kerb and channel, footpaths and associated stormwater.

Total cost of proposed project is $274,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.