• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish February 2015 - June 2024
  • Estimated project cost $324,730,000
  • Australian Government contribution $324,730,000
  • State QLD

Project description

This package of works will construct new overtaking lanes along the Bruce Highway in areas that lack overtaking opportunities. Overtaking lanes can be added to high-speed two-lane roads in situations where overtaking of slower moving vehicles is only possible when there is a suitable gap in the oncoming traffic and sufficient sight distance at a location.

Benefits

The new overtaking lanes will provide increased safety, travel efficiency and reduced motorist frustration particularly on routes that carry significant numbers of freight and recreational vehicles.

Funding

The Australian Government is fully funding the $324.73 million Bruce Highway Overtaking Lanes package.

Timetable

Construction commenced in February 2015 and was completed in June 2024.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.