• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2014 - May 2015
  • Estimated project cost $41,113
  • Australian Government contribution $40,000
  • Local Council/Shire Eurobodalla Shire Council
  • State NSW

Project description

Narrow, worn gravel pavement showing significant loss of material

Works will comprise of the breaking up and loosening of the existing road surface, material, placement of compaction of new material, road widening to 5 metres and re-establishment of table drains and roadside clearing, some 6500 square metres

Total cost of proposed project is $41,113

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.