• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2015 - Sep 2015
  • Estimated project cost $575,000
  • Australian Government contribution $575,000
  • Local Council/Shire Huon Valley Council
  • State TAS

Project description

The existing road is deficient in strength.

Existing base will be lime based stabilised, 120mm thick layer of compacted finely crushed rock and finished with a two coat seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.