• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2014 - Mar 2015
  • Estimated project cost $181,997
  • Australian Government contribution $178,980
  • Local Council/Shire Town of Cambridge
  • State WA

Project description

Aged, rough and cracked asphalt seal. Need to replace low kerb on east side because otherwise the resurfacing will leave only 30mm kerb height.

Resurface road with asphalt. Replace kerb on east side only. Length 745m. Width 6.6m.

Total cost of proposed project is $181,997

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.