• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2014 - Dec 2014
  • Estimated project cost $243,031
  • Australian Government contribution $237,080
  • Local Council/Shire Shire of Carnarvon
  • State WA

Project description

Some sections of this road have been re-sheeted in the past ten years however these are starting to blowout in places, as maintenance grading cuts away the depth of sheeting. The areas of road that have not been re-sheeted are not responding to maintenance grading as the sub grade has broken through to the native sands below and have become dangerous.

Between SLK 0 and 40, there will be 2.5 km of road that gets Ripped, Rotary-Hoed, then Rolled, over 1.5km of road that is reformed and nearly 15km of road that receives re-sheeting – or more depending on remaining funds.

Total cost of proposed project is $243,031

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.