• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2015 - May 2015
  • Estimated project cost $23,045
  • Australian Government contribution $23,045
  • Local Council/Shire Narrandera Shire Council
  • State NSW

Project description

Insufficient pavement strength, frequent potholes and deep rutting

stabilize 50 mm top pavement layer using Polycom. Provide 1 % polycom, rip 50 mm and recompact.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.