• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2014 - Mar 2015
  • Estimated project cost $266,165
  • Australian Government contribution $266,165
  • Local Council/Shire Derwent Valley Council
  • State TAS

Project description

Stormwater flooding due to inadequate drainage causing damage to kerb and channel and footpath. This has resulted in dangerous situation for pedestrians, residents and drivers due to water escaping and running across the road.

New 375 diameter stormwater pipe of 170 metres, 560 metres of kerb and channel, new grated side entry pits quantity 8,plus pavement stabilisation and sealing.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.