• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2015 - Jun 2015
  • Estimated project cost $555,035
  • Australian Government contribution $322,744
  • Local Council/Shire Brimbank City Council
  • State VIC

Project description

The existing road pavement exhibits oxidation and areas of significant longitudinal and crocodile cracking, loss of aggregate and patching. In addition the road has no underground drainage.

It is proposed to rehabilitate 330 metres of existing road pavement and resurface with asphalt, reconstruct 668 metres of existing kerb and channel, reconstruct existing vehicle crossings where required, construct 514 metres of underground drainage works and reconstruct of all footpath.

Total cost of proposed project is $555,035

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.