• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2015 - Dec 2015
  • Estimated project cost $273,460
  • Australian Government contribution $273,460
  • Local Council/Shire Gwydir Shire Council
  • State NSW

Project description

The sealed road pavement has become significantly deteriorated and deformed by traffic and weather requiring elevated maintenance and making the road rough for travellers.

Rip and reshape existing pavement and recycle as subbase. Construct a new 150mm base layer and apply a two coat bitumen seal to create a smooth all weather wearing surface suitable for High Productivity Vehicles such as Road Trains.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.