• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2015 - Oct 2015
  • Estimated project cost $333,422
  • Australian Government contribution $333,422
  • Local Council/Shire Southern Downs Regional Council
  • State QLD

Project description

The narrow 3.7m single lane road is a safety concern for passing vehicles (speed limit is 100 kilometers per hour) and widening of the road would improve road safety. Also worn pavement and uneven pavement surface cause inconvenience to motorists and there is a potential for run off road accident. To overcome this, some sections of the uneven surface (especially at bends) will be reshaped.

• Formation widening from 5.4 metres to 7.4 metres. • An Overlay of gravel up to 140 millimetres at various sections to improve strength of the pavement & ride quality. • Seal widening from 3.7 metres to 6.2 metres. • Reforming table drains to improve the drainage.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.