• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2015 - Feb 2015
  • Estimated project cost $200,000
  • Australian Government contribution $100,000
  • Local Council/Shire Ballina Shire Council
  • State NSW

Project description

The section of road comprises failed basecourse pavement, and is a significant maintenance burden.

The proposed work comprises excavation and removal of failed basecourse pavement and replacement of basecourse pavement for the road width of approximately 9 metres and length of 480 metres, plus installation of subsoil drainage for 480 metres.

Total cost of proposed project is $200,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.