• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2018 - May 2019
  • Estimated project cost $3,500,000
  • Australian Government contribution $1,919,088
  • Local Council/Shire Maroondah City Council
  • State VIC

Project description

The Lincoln Road road surface is showing signs of deterioration, and this is being further exacerbated by the absence of kerb & channel and underground stormwater drainage infrastructure.

Construction of kerb & channel, stormwater drainage infrastructure, and the renewal of the existing road pavement to provide enhanced longevity for this section of Lincoln Road. In addition, the works will include improvements to the intersections associated with the adjoining local streets.

Total cost of proposed project is $3,500,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.