• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2015 - Oct 2015
  • Estimated project cost $59,686
  • Australian Government contribution $59,686
  • Local Council/Shire Brewarrina Shire Council
  • State NSW

Project description

An existing formed road becomes impassable in wet weather with deep scouring, and drainage needing to be rectified.

Re-form and re-sheet existing section of road, rectify drainage providing all weather access for the treated section.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.