• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2015 - Feb 2016
  • Estimated project cost $175,762
  • Australian Government contribution $175,762
  • Local Council/Shire City of Bunbury
  • State WA

Project description

Pavement failure has been caused by the entry of moisture into the road pavement.

The pavement section requires a reconstruction with a replacement kerb, reseal and reinstatement of verges and adjacent path.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.