• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2015 - Feb 2016
  • Estimated project cost $542,907
  • Australian Government contribution $266,460
  • Local Council/Shire Bankstown City Council
  • State NSW

Project description

Pavement distress and fatigue cracks at most of the sections. Damaged kerb & gutter and no kerb ramp access.

Full width pavement resurfacing and kerb & gutter reconstruction

Total cost of proposed project is $542,907

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.