• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2015 - Feb 2016
  • Estimated project cost $179,194
  • Australian Government contribution $179,194
  • Local Council/Shire Town of Claremont
  • State WA

Project description

Following 2012 assessment by Opus the road network was prioritised based on asphalt condition, cracking, patches, local surface defects, rutting and traffic counts. The list of roads were then inspected for deterioration since the survey. cost of annual maintenance and drainage problems. This road has potholes, edge failure, displaced kerb and cracking

Remove 40mm of seal, replace with new asphalt layer and new kerbing

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.