• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2016 - Jun 2016
  • Estimated project cost $448,513
  • Australian Government contribution $288,941
  • Local Council/Shire City of Boroondara
  • State VIC

Project description

Loss of shape of road surface, kerb and channel in poor condition due to missing and disjointed sections. Drains to be updated

Install new storm water drainage, remove and relay kerb and channel to match new road surface levels. Infill areas between kerb and channel and the existing road base and resurface road

Total cost of proposed project is $448,513

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.