• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2015 - Jun 2016
  • Estimated project cost $542,741
  • Australian Government contribution $542,741
  • Local Council/Shire Narromine Shire Council
  • State NSW

Project description

Narrow formation width of 6m. Narrow bitumen seal of 3.5 m, Significant pavement failure, edge drop off. School Bus Route and Heavy vehicle route between production areas into Trangie.

Widen formation to 8m, Rip, reshape existing road and overlay with gravel pavement 0.15 m thick. Provide bitumen seal 6.5m wide. We only propose to do a single coat (primer) seal in this instance and to do the second seal coat approx 12 months later as a separate project

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.