• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2016 - Apr 2016
  • Estimated project cost $286,883
  • Australian Government contribution $283,344
  • Local Council/Shire Bankstown City Council
  • State NSW

Project description

Pavement surface ravelling and failure at few sections

Pavement resurfacing and reconstructing damaged kerb & gutter sections

Total cost of proposed project is $286,883

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.