• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2015 - May 2016
  • Estimated project cost $102,162
  • Australian Government contribution $102,162
  • Local Council/Shire Town of Victoria Park
  • State WA

Project description

Asphalt oxidised due to age, significant patching and medium to high level cracking to 70% of asphalt surface

Mill out 15mm – 20mm existing asphalt and apply 30mm SMA Asphalt . Due to a very thin layer of existing asphalt wearing course an overlay may be applied in some sections to ensure minimal disturbance to the existing base material . Kerbing to be replaced where required

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.