• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2015 - Nov 2015
  • Estimated project cost $560,000
  • Australian Government contribution $560,000
  • Local Council/Shire Liverpool City Council
  • State NSW

Project description

Pavement has reached the end of the serviceable life and is demonstrating signs of extensive cracking, rutting and failures.

Pavement reconstruction with 80mm asphalt concrete for full length Bobin Road between Charter Street and Heckenberg Avenue including reconstruction of deteriorated sections of kerb and gutter and layback. Selected section of Bobin Road is to be reconstructed with 100mm asphalt concrete.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.