• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2015 - Oct 2016
  • Estimated project cost $268,116
  • Australian Government contribution $268,116
  • State NT

Project description

Damaged section of 210 m of road and 500m of shoulder; cracks on the sealed road, numerous pot holes, more pedestrian movement area.

Drainage Works Cleaning out of 4 x culverts both ends Concrete Footpath on Headwalls & Install Hand Rails on sides of 4 x culverts Regrade of existing drainage along roadway Install 300mm Stormwater pipe, Form and Pour 2 x Headwalls at bad floodway @ VOQ intersection Construct relief drain from new culvert @ VOQ intersection beside playground to main town drain

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.