• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Apr 2016
  • Estimated project cost $363,529
  • Australian Government contribution $363,529
  • Local Council/Shire Penrith City Council
  • State NSW

Project description

The road was originally constructed in 1975 and is already failed with numerous potholes and patching due to the increasing traffic and inadequate pavement materials

It is proposed to heavy patch and 50mm overlay for a length 340 metres between Bridge and St Clair Avenue and to mill 130mm and replace with 130mm deeplift asphalt for a length of 440 meters between St Clair Avenue and Endeavour Avenue and a width of 13 metres.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.