• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2015 - Nov 2015
  • Estimated project cost $10,429
  • Australian Government contribution $10,429
  • Local Council/Shire Shire of Mt Marshall
  • State WA

Project description

The surface can be quite slippery when wet due to the surface being primarily clay

Construct a new 9.0 metre wide 150 millimetre thick compacted gravel pavement carriageway for a total of 300 metres. New gravel will be imported, spread, water bound and compacted to achieve the designated surface.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.