• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2015 - Dec 2015
  • Estimated project cost $59,926
  • Australian Government contribution $59,926
  • Local Council/Shire Mid-Western Regional Council
  • State NSW

Project description

A pavement rehabilitation project was completed in 2014/15 where a primer seal was used.

This year a final seal will be placed on the primer seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.