• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Apr 2016
  • Estimated project cost $90,900
  • Australian Government contribution $90,000
  • Local Council/Shire Wodonga City Council
  • State VIC

Project description

Road pavement shows significant areas of failure, including shoving, cracking and potholing. High maintenance costs associated with ongoing inspection and repair. Road safety associated with very slick pavement surface and shoved pavement.

Intersection reconstruction, including removal and replacement to 50mm depth of 2750 sqm of existing failed wearing surface. Pavement and/or subgrade replacement as required, Supply and place 50mm thick layer of type H 320 bitumen asphalt. Repaint linemarking.

Total cost of proposed project is $90,900

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.