• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2016 - Aug 2016
  • Estimated project cost $165,550
  • Australian Government contribution $84,326
  • State SA

Project description

Significant sheeting failure inpacting sub course, vehicles speed is impaired possible loss of control at posted speed.

Road has graded sheeted surface which requires renewal, proposed to resheet the surface and rectify sub course damage.

Total cost of proposed project is $165,550

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.