• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2016 - Apr 2016
  • Estimated project cost $308,184
  • Australian Government contribution $308,184
  • Local Council/Shire Greater Shepparton City Council
  • State VIC

Project description

base and pavement failure/ inadequate drainage /shoving / depressions

Replace failed Kerb and channel and stabilise full length of street 200mm depth @ 2.5% cement due to pavement failure , supply and lay 10H asphalt 40mm depth (2485m2)

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.