• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2016 - Sep 2016
  • Estimated project cost $273,969
  • Australian Government contribution $273,969
  • Local Council/Shire Hawkesbury City Council
  • State NSW

Project description

Substantial pavement failure including pot holes, cracking and rutting.

Rehabilitate failed sections

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.