• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Jun 2016
  • Estimated project cost $360,000
  • Australian Government contribution $300,000
  • Local Council/Shire Monash City Council
  • State VIC

Project description

The road surface is showing signs of significant deterioration with poor shape, potholes and access problems. In addition street trees are lifting the footpath and kerb and channel. This has led to the kerb and channel holding water. The existing drainage is insufficient for the road.

Reconstruction/rehabilitation of the existing road pavement, kerb and channel and driveways to address pavement failure, shape, crossfall and failing kerb and channel. Provision of additional drainage to correct the drainage deficiency. The section of road being worked on is 9.3m wide and is approximately 178m in length

Total cost of proposed project is $360,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.