• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2015 - Jun 2016
  • Estimated project cost $294,847
  • Australian Government contribution $294,847
  • Local Council/Shire Cobar Shire Council
  • State NSW

Project description

Road has deteriorated due to loss of gravel causing rutting, corrugations and exposure of larger stones. This is a school bus route and vehicle safety is a concern.

Supply, spread and compact 150 mm of gravel

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.