• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2016 - Apr 2016
  • Estimated project cost $203,067
  • Australian Government contribution $203,067
  • Local Council/Shire Sutherland Shire Council
  • State NSW

Project description

Road pavement base course has degraded, causing the wearing surface to crack severely. Existing wearing surface severely oxidised, potholes in patches.

Heavy patching of 125 sq.m pavement area with 120mm asphalt concrete and then re-surfacing entire section (3250 sq.m ) with 40mm thick asphalt concrete overlay.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.