• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2016 - Jan 2017
  • Estimated project cost $63,053
  • Australian Government contribution $21,018
  • Local Council/Shire Shire of Peppermint Grove
  • State WA

Project description

Reseal uneven bitumen road

Profile existing seal and replace with 30 mm thick black asphalt - total area of 1,430 square metres

Total cost of proposed project is $63,053

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.