• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Jun 2016
  • Estimated project cost $279,238
  • Australian Government contribution $279,238
  • Local Council/Shire Bellingen Shire Council
  • State NSW

Project description

Existing bridge has been closed due to significant structural problems. A detour diversion is in place adding 30kms to journeys

Replace existing one lane timber bridge with a new steel and concrete bridge, raise deck level by one metre to improve flood resilience.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.