• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2016 - Jun 2017
  • Estimated project cost $101,530
  • Australian Government contribution $66,953
  • State VIC

Project description

Bridge abutment area has depleted rock beaching. Steel components showing signs of rust. Several expansion joints need replacement.

Stabilise bridge abutments by supplying and placing rock beaching on batters only, 2.5m upstream and downstream. Remove rust and paint bearers of the bridge. Reinstate expansion joints that have failed in bridge deck. Reinstate lost fill and correct drainage at south approach along guard rail.

Total cost of proposed project is $101,530

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.