• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2016 - Nov 2016
  • Estimated project cost $890,147
  • Australian Government contribution $890,147
  • Local Council/Shire Northern Territory of Australia
  • State NT

Project description

Bullita Access Road provide access to two major indigenous communities and tourists. More than 5,000 tourists visit Bullita Homestead annually. Various complaints have been received from two local indigenous communities and various other road users/tourists regarding sections becoming impassable during the wet season and afterwards.

Construct six concrete inverts on the Bullita Access Road at chainages 7.17, 7.36, 9.22, 9.33, 10.24 and 10.33 kilometres.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.