• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2016 - Nov 2016
  • Estimated project cost $31,605
  • Australian Government contribution $31,605
  • Local Council/Shire Weddin Shire Council
  • State NSW

Project description

This section of Driftway Road was widened and primersealed in April 2015. Final seal needs to be placed prior to the failure of the primerseal.

It is intended to seal 7350 m2 with a 10mm sprayed bitumen seal. Site preparation will include pothole & edge patching, preparation of stockpile site for aggregates and sweeping off excessive loose materials.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.