• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2016 - May 2016
  • Estimated project cost $71,626
  • Australian Government contribution $65,654
  • Local Council/Shire Shire of Merredin
  • State WA

Project description

The primer seal has begun to break up due to heavy traffic movements and major patching is now required.

Reseal a 3.3 kilometre section of Nokaning West Road with a 98/2 cutback bitumen and cover with a 10mm aggregate.

Total cost of proposed project is $71,626

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.