• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2016 - Nov 2016
  • Estimated project cost $414,960
  • Australian Government contribution $414,960
  • State NSW

Project description

Pavement surface is fatigue, aged and block and crocodile cracks. Rutting along the wheel paths.

Deep lift pavement rehabilitation is required as per the pavement design, 180mm thick AC with multiple base course layers.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.