• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2017 - Sep 2018
  • Estimated project cost $700,681
  • Australian Government contribution $120,000
  • State NSW

Project description

Kerb and gutter drains poorly, street has no piped drainage system and footpath is dangerous for pedestrians

Renew concrete kerb and gutter over a 250m length including reconstructing the adjacent asphalt footpath paving, reconstruction of the adjacent road shoulder/parking lane and installation of kerb inlet pits with new piped drainage.

Total cost of proposed project is $700,681

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.