• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2017 - May 2017
  • Estimated project cost $350,000
  • Australian Government contribution $174,851
  • State QLD

Project description

Existing road condition assessed as very poor condition. Kerb and channel is also in very poor condition resulting in further damage to pavement during wet weather events.

Proposed scope includes full reconstruction of Sealed Pavement to the existing standard, and demolition and replacement of kerb and channel including any associated drainage structures.

Total cost of proposed project is $350,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.