• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2017 - May 2017
  • Estimated project cost $110,187
  • Australian Government contribution $110,187
  • Local Council/Shire Southern Mallee District Council
  • State SA

Project description

Road surface has deteriorated due to loss of rubble over the years

Resheeting failed section of 4km with a width of 7metres by providing compacted rubble to a depth of 150mm

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.