• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2017 - May 2017
  • Estimated project cost $423,160
  • Australian Government contribution $265,000
  • Local Council/Shire Mosman Municipal Council
  • State NSW

Project description

Deteriorated road surface and base failure. The formation is due for reconstruction.

Replacement of pavement up to 170mm with asphalt AC20HD and AC10HD wearing course. Sections where the surface shows better performance, replacement of 50mm AC10HD wearing course. Repair of some of the stormwater assets will also be done in the project.

Total cost of proposed project is $423,160

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.