• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2016 - May 2017
  • Estimated project cost $300,000
  • Australian Government contribution $100,000
  • State NSW

Project description

Gravel has washed away and deteriorated to a state it no longer provides a safe trafficable journey particularly when it is wet, drainage needs correcting, formation requires reshaping.

Undertake formation reconstruction, drainage improvements, and gravel re sheeting of 4.2 kilometres at 100mm thick x 7mtrs wide.

Total cost of proposed project is $300,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.